SMED · Changeover Analysis

Welder 07 · 12 May · 08:42 → 09:00 · PN-7733 → PN-4521
Total time
18:24min
Target: 12:00
vs Target
+6:24min
53.0%
Internal setup
11:42min
63% of total
External setup
6:42min
37% — could be done while running

Phase timeline (target overlay)

InternalExternalTarget
TARGET 12:0012:0010:42Announce21:18Wait clear33:42Remove tool42:48Fetch new53:18Install61:48Configure70:36Trial84:12First good00:0018:24+6:24 OVER

Internal vs External breakdown

Internal (machine stopped)11:42 (63%)
External (could be while running)6:42 (37%)

Compare

This changeover18:24
Last (10 May)16:48
30-day avg15:32
Target12:00
Best ever (24 Apr)09:18
World-class (theoretical)06:00

Step-by-step breakdown

#StepTypeStartEndDurationTargetΔTag
1Announce + safety checkEXT08:4208:430:420:30+0:12
2Wait for last part to clearINT08:4308:441:181:00+0:18
3Remove old tool · Welder 07KAIZENINT08:4408:483:422:30+1:12
4Fetch new tool from rack 2BKAIZENINT08:4808:512:480:00+2:48OVER
5Install new toolINT08:5108:553:183:00+0:18
6Configure controller (recipe)KAIZENEXT08:5508:571:480:00+1:48
7Trial run + adjustINT08:5708:580:361:30−0:54
8First good part — QA sign-offINT08:5809:004:124:00+0:12