⌘ K
Asset Hierarchy
Define Enterprise → Site → Area → Line → Cell → Machine. Drag to reorganize.
🌐Astrem Manufacturing
🏭Chonburi Plant
📍Stamping Area
⚙Line A1 — Assembly
🔩Press 01
🔩Press 02
⚙Line E5 — Press
📍Welding Area
⚙Line B2 — Welding
🔩Welder 04
🔩Welder 07
🔩Welder 11
⚙Line C3 — Final QC
📍Assembly Area
🏭Rayong Plant
Line · CHB-01 · Welding
Line B2 — Welding
Display name (EN)
Line B2 — Welding
Display name (TH)
สาย B2 — เชื่อม
Asset code
CHB-01-WELD-B2
Type
Line
Capacity (parts/hr)
180
Ideal cycle time (s)
20.0
Target OEE
75 %
Stretch OEE
82 %
PLC tag
CHB.B2.STATE
Calendar
Default 3-shift
Validation
✓3 machines have PLC tags configured
✓No circular references
!Welder 11 has no ideal cycle time set
Machines under this line
| Code | Name | PLC tag | Cycle | Order | |
|---|---|---|---|---|---|
| W04 | Welder 04 | CHB.B2.W04.STATE | 38.0s | 1 | |
| W07 | Welder 07DOWN | CHB.B2.W07.STATE | 41.7s | 2 | |
| W11 | Welder 11INCOMPLETE | — | — | 3 |